Is typically not referred to as a buffer type in critical chain project management?

Respuesta :

dinosaurbarn
dinosaurbarn dinosaurbarn
  • 14-01-2018

The answer is Free Buffer. Project buffer, a not usual and the only one buffer to protect the project deadline;

Feeding buffer it is different types of buffers to protect parts of the critical chain. And resource buffer is a multiple artificial buffers that act as warning signals to assure that it is available of resources.

Answer Link

Otras preguntas

Jack jogged at an average speed of 12 kilometer per hour from his home to the nearby park and joggedback at an average of 7 km/ hour with the same route. If he
Methodology A. Preparation of Setup for Paper Airplane
decrease 380 by 2.9%
“Una gota de sangre” Ángela Hernández Núñez análisis literario
Write a letter to the Manager, Taj International, and Lucknow to find out the rates for conducting the wedding Reception of your sister, enquiring specifically
answer to During an action potential, which ion primarily enters the neuron, leading to depolarization? A) Sodium (Na+) B) Potassium (K+) C) Calcium (Ca2+) D) C
Part A In this problem the Townsends are a family of 5 and they’re going to the movie theater there’s 2 adults and three kids and he’s going to buy a large drin
People do not experience age-related vision changes until the sixties.a.Falseb.True
What is the domain of theWhich equation is the inverse of y = 100 – x2? function y = StartRoot x + 6 EndRoot minus 7?
How many pairs of vertical angles are there9