In the execution phase of a project's life cycle, activities are guided by decisions that were made in the __________ phase.

Respuesta :

MissPhiladelphia
MissPhiladelphia MissPhiladelphia
  • 14-02-2017
The choices can be found elsewhere and as follows:

A.initiating
B.planning
C.monitoring/controlling
D.closing
E.assessment

I believe the correct answer is option B. 
In the execution phase of a project's life cycle, activities are guided by decisions that were made in the planning phase. Hope this answers the question.
Answer Link

Otras preguntas

What is the sum of the arithmetic series below? -100 + -95 + -90 + -85 + ... + -5 + 0 + 5 + ... + 85 + 90 + 95 + 100
How do you find the area of a circle
what term describes the tendency of a moving object to continue moving at the same velocity unless an unbalanced force acts on it? A. inertiaB. Friction C. Grav
how would it be x=3 when thats not an option???
A pair of designer sunglasses was marked up 10% and is now selling for $165.00. What was the original price of the sunglasses?
Which of the following populations would be least likely to survive a change in its ecosystem?
A simpler one for the word rain and it has to be single word
Find the measure of angle x in the figure below: 65° 70° 110° 125°
The circulatory system keeps the body and its tissues continuously oxygenated. It does this by having A) veins to carry both oxygenated blood to the tissues an
A child in a swing oscillates with a certain frequency of oscillation (the child is sitting still. another child sits next to the first child. how does the swin