It takes 12 men 5 days to complete a job. Work out how many days it would take 3 men to complete the same job.

Respuesta :

Esther
Esther Esther
  • 03-03-2022

Answer:

20 days

Step-by-step explanation:

It takes 12 men 5 days to complete a job. Work out how many days it would take 3 men to complete the same job.

12 * 5 = 60

60/3 = 20

It will take 3 men 20 days to do the same job

Answer Link

Otras preguntas

what does 3,676,487 rounded to the nearest thousand?
simplify each equation, then solve. 1) log 2 128=x
In the putting out system raw wool was distributed to what
4(1-3n)-14> 4(2n+3)-9n
how many miles does the huang-he river stretch across northern china?
A life cycle in which organisms switch back and forth between diploid and haploid stages A. is a haploids life cycle B. is a diploids life cycle C. is an altern
what events inspired independence movements in Latin America?
Which set of descriptions would describe the largest number of people in a region? A. Rural, Sunni, and Kurd B. Urban, Sunni and Arab C. Rural, Shia, and Kurd D
Oxygen is denoted as 16O *. How many protons and neutrons does an oxygen atom have?
what is the easiest way to go this math problem 8tr+10t +14t + 13