It take 4 people 40 minutes to clean a garden. How long will it take 6 people to clean the same garden

Respuesta :

loconte loconte
  • 02-07-2021

Answer:

4/9 of an hour (26.666 minutes)

Step-by-step explanation:

4 * x * 40/60 = 1

x * 160/60 = 1

x=60/160 = 6/16 = 3/8 (this is the rate for one worker)

~~~~~~~~~~~~~~~~

6 * (3/8) * x = 1

x = 4/9

Answer Link

Otras preguntas

Rank these graphs on the basis of the angular acceleration of the object. Rank positive angular accelerations as larger than negative angular accelerations. P
the cake looked too good to eat. what is the adverb
What is the surface area of a package that is 8 inches by 11 inches by 2 inches
If parallelogram JKLM is rotated 270° counterclockwise around the origin, what are the coordinates of the endpoints of the side congruent to side KL in the imag
the temperature dropped 2*F each hour for 6 hours. What was the total change in temperature?
How does an acid–base indicator react when placed in an acidic solution?
The volume of a cone is 62.8 cubic inches. The height of the cone is 15 inches. What is the radius of the cone, rounded to the nearest inch? Use π = 3.14. A 2
Sales tax is calculated as a percentage of the sales price. If sales tax is 5%, what is the sales tax on clothing that costs $170? $8.50 $10.50 $15.00 $17.50
" Pentagon ABCDE and pentagon A’B’C’D’E’ are shown on the coordinate plane below. Which two transformations are applied to pentagon ABCDE to create A’B’C’D’E’?
how do u solve d÷12=2